Assignment 2: LASA – Project Planning – Developing the Project Plan and Determining Critical Path
Using the District4WarehouseMove WBS.xls provided, create a Microsoft project plan for the District 4 Warehouse Move project. Use the PDF document, Project Plan Check – District4Move, to check your work to be sure you have created your starting project plan correctly. Microsoft Project is required for this task. If you have not yet downloaded OpenProj, please click here and follow the directions to do so now.
Note: you will need to insert a column to include your WBS codes, then you will need to sequence the tasks to show tasks by work package. It may help to review the Microsoft tutorial, Sequencing tasks in a project: http://www.project-open.org/en/project_tutorial
Based upon the details in the WBS and the project case, determine which tasks need to be completed first and which tasks are dependent upon other tasks to be completed prior to starting. Using this information identify predecessors in your project plan’s predecessor column. Complete the predecessor column by entering the line number of tasks that must be completed in order for each task to start. This will create your project timeline.
Using the View Network Diagram functionality within MS Project, determine the critical path for this project. In a MS Word document, list the activities that are on the critical path. Considering the risks identified in the risk table below, identify which risks would be most likely to increase your project timeline. Justify your responses.
Submit both your completed project plan and your MS Word document.
District 4 Production Warehouse Move Project – Risk Table
1
Permits are not received per the schedule
2
Finish work contractors walk off the job half way through
3
Framing and drywall contractors are running behind schedule and can only produce half their crew as scheduled
4
Work benches are poor quality and 1/3 will have to be rebuilt
Submit your plan to M3: Assignment 2 Dropbox by Wednesday, August 6, 2014.
Assignment 2 Grading Criteria
Maximum Points
Correctly developed a project plan from the WBS provided
60
Completed the predecessor column correctly in the project plan based upon information in the case.
40
Correctly identified critical path activities
16
Correctly identified risks that would impact the project schedule
40
Used proper writing components such as, correct grammar, spelling, and word choice and cited all sources using correct APA style, etc..
Absolutely spot on. I have had the best experience with Elite Academic Research and all my work have scored highly. Thank you for your professionalism and using expert writers with vast and outstanding knowledge in their fields. I highly recommend any day and time.
Stuart L
Thanks for keeping me sane for getting everything out of the way, I’ve been stuck working more than full time and balancing the rest but I’m glad you’ve been ensuring my school work is taken care of. I'll recommend Elite Academic Research to anyone who seeks quality academic help, thank you so much!
Mindi D
Brilliant writers and awesome support team. You can tell by the depth of research and the quality of work delivered that the writers care deeply about delivering that perfect grade.
Samuel Y
I really appreciate the work all your amazing writers do to ensure that my papers are always delivered on time and always of the highest quality. I was at a crossroads last semester and I almost dropped out of school because of the many issues that were bombarding but I am glad a friend referred me to you guys. You came up big for me and continue to do so. I just wish I knew about your services earlier.
Cindy L
You can't fault the paper quality and speed of delivery. I have been using these guys for the past 3 years and I not even once have they ever failed me. They deliver properly researched papers way ahead of time. Each time I think I have had the best their professional writers surprise me with even better quality work. Elite Academic Research is a true Gem among essay writing companies.
Got an A and plagiarism percent was less than 10%! Thanks!